Roof Replacement With Solar Panels: What to Coordinate Before Work

Updated November 4, 2026 6 min read Golini Roofing, Wakefield MA

A roof replacement with solar panels already on the roof involves two companies: your roofer and whoever owns or services the solar system. Before you accept a start date, get both of them to agree in writing on who takes the panels off, where they are stored, who handles the mounts and flashing where the system meets the roof, and who puts everything back and confirms the system works. Don't assume the roofing contract covers solar work, or that the solar company will schedule around your roofer.

This checklist is for homeowners in Wakefield and around the North Shore who have panels on a roof that now needs replacing. It shows what to ask each company, in what order, so the job doesn't stall between them.

Tell your roofer about the panels at the first call

Mention the solar system when you ask for an estimate, not after you've picked a date. Panels change how much of the roof can be seen and reached, and they affect scheduling. When we come out for a free written estimate, we look at the roof in person before pricing anything, and knowing about the system ahead of time helps us look at the right places: the roof surface around the arrays, the flashing, and any signs of leaks near the mounts. Share the solar company's name and contact, and any installation paperwork you have.

Ideally the roof and the panels are planned together from the start. ENERGY STAR advises that if a roof needs work, it makes sense to replace it before installing solar panels so they don't have to be removed and reinstalled later, and to ask your roofer to come back after installation to make sure the panels didn't damage the roof (ENERGY STAR, rooftop solar). If your panels are already up, the remove-and-reinstall step is the part that needs the most coordination.

Find out who owns the system and what the agreement says

Pull out the paperwork for your solar system. Some homeowners own their panels outright; others have a lease or a power purchase agreement with a solar company that owns the equipment. That difference decides who is allowed to touch the system. Call the current service contact (which may not be the original installer) and ask:

  • Who can authorize work on the system?
  • Who is allowed to remove, store, reinstall and recommission the panels?
  • What notice or paperwork do they need before roofing starts?
  • How does removing and reinstalling affect the solar equipment warranty, and does the agreement require a particular company to do it?
  • What does removal and reinstallation cost, and who pays?

Get the answers in writing, tied to your actual agreement. "This is routine" is not the same as a confirmed scope.

Agree on who handles the panels and the roof underneath

Panel removal, electrical disconnection and reinstallation are solar work. Leave them to the solar company or the contractor it names, and never climb up or disconnect anything yourself. Ask that company for a written scope that says who removes the panels, where they will be stored (on site or off), who is responsible if anything is damaged while they are down, and when they will be reinstalled.

The part most likely to fall between two contracts is the spot where the solar mounts go through the roof. Ask both companies who is responsible for:

  • the existing mount locations and any holes left in the old roof deck;
  • flashing around the new mount attachments when the panels go back up;
  • any change to where the racking attaches;
  • wiring that runs across or through the roof.

On our roof replacements we usually tear off down to the deck, repair any damaged wood, put down new underlayment and ice shields, and replace worn flashing at chimneys, skylights, walls and valleys. With an existing solar system, ask us and the solar company to line up those steps with theirs so each piece of work is covered by one of the two scopes, and nothing is left out because each company thought the other had it.

Plan the handoffs, not just the dates

A roof replacement with solar usually runs in three stages: panels come off, the roof is replaced, panels go back on. Each stage should have a clear signal that it is done before the next begins.

StageWho confirms itWhat to get in writing
System shut down and panels removedSolar companyDate removed, storage location, condition of equipment
Roof ready for roofingRooferStart date, roof areas involved, access and delivery areas
Roof complete and ready for panelsRooferCompletion note and any work still open
Panels reinstalled and flashedSolar company (and roofer for roof details, if agreed)Reinstall date, who flashed the mounts, any inspection needed
System back in serviceSolar companyConfirmation the system is producing, any utility or town sign-off

Ask each company which permits or inspections apply to its part of the job and who arranges them. In Massachusetts, permits are issued by your town's building department, so ask rather than assuming what one town requires matches the next.

Keep both companies in the loop when the schedule moves

New England weather moves roofing dates. A rainy week in spring or a nor'easter in the fall can push the start, and once the panels are off, the system isn't producing until they're back. Decide up front whether the two companies will talk directly or through you. If you relay messages, ask each to confirm they got them. If the panels are already down when a delay hits, confirm who is still responsible for storing and protecting them. Our post on roof replacement weather delays covers that conversation in more detail; add the solar company to the list of people who need to hear about changes.

For getting the house ready (clearing the driveway, protecting the attic, moving things away from the walls), use the roof replacement readiness checklist, and agree with both companies on where each one parks, stages equipment and stores panels.

Close out with two sets of paperwork

Roof done and solar done are separate milestones. Keep the roofing completion records and the solar reinstallation records apart so one is never mistaken for the other. Save the agreed scopes, any changes and the handoff confirmations in your roof replacement records, and ask both companies what their warranties cover now that the system has been off and on the roof. Our roof warranty questions help with the roofing side.

Common questions about roof replacement with solar panels

Do solar panels have to come off for a roof replacement?

Generally yes, the roof under the arrays has to be reached to be replaced. Who removes and reinstalls them depends on your solar agreement, so confirm it with the system owner or solar company first.

Who removes and reinstalls the panels?

Usually the solar company or a contractor it names, depending on your solar agreement. Confirm it with the system owner before you set a roofing date, and tell your roofer who it is at the estimate.

Should I replace my roof before installing solar?

If the roof needs work, ENERGY STAR recommends replacing it before the panels go up, so they don't have to come off again later.

Who is responsible for leaks around solar mounts after reinstallation?

Whoever did the flashing at the mounts, as written in the agreed scopes. Settle that in writing before work starts so you know who to call.

If your roof in Wakefield or a nearby North Shore town has panels on it and needs replacing, request a free estimate or call (781) 246-0141. Tell us about the system when you call, and we'll look at the roof in person and talk through how to coordinate with your solar company.

Golini Roofing trucks parked along a residential street
Free estimate

Questions about your roof?

Golini Roofing has worked on roofs across Wakefield and the North Shore since 1982. Every roof is priced after we see it, and the written estimate is free.